On December 16th,2007 17:58PM, fireworks and firecrackers lighted up at Xiangfeng project site exactly at the moment of the last large roof board firmly hanged onto the roof beam, which shows that the main building"s structural roof-sealing of 8000t/a Cigarette Paper Project of Hunan Xiangfeng Special Paper Co., Ltd was achieved successfully.
The EPC contract of this project was signed on November 28 th, 2006. project commenced on January 28th, 2007. On June 25th, 2007, commencement ceremony of civil works was held and then construction formally started. Under CEC leaders’ instructions, owing to joint efforts by project management team, supervising company, construction company and the Owner’s cooperation, CEC overcame difficulties such as complex geological conditions and shortage of water, electricity, diesel, cement and sandstone etc., completed the piling works on September 19 th, 2007, the second floor construction of stock preparation & paper making plant on November 18 th and prefabricated abdominal thin beams, gutter board and roof board hoisting finished on December 16 th and the main building was successfully capped.
Smooth roof-sealing of the main building of Hunan Xiangfeng project, with great significance, has taken a crucial step forward into on-time completion and hand-over of the project and also provided the erection work with a favorable working condition.
The Owner, local government officials, CEC vice president Mr. Tan Shengxi, Director of Project Contracting Department Mr. Wang Jianming, project manager Mr. Li Jinggang and his team members and concerning subcontractors all witnessed such a significant milestone moment.